Experiment 5 Proposal
Objectives:
- Commission MCP-PMT-based x-ray monitoring with PSEC-4 readout
- Study yie
Beam request: all
background monitoring can be done parasitic with other machine
operations. 2x dedicated 5
minute bremsstrahlung target in runs
Experiment 5 Execution Plan
This part needs to be filled in. Action items from previous week:
- Mechanical drawing (review and get machining started) [Joachim is lead, sharing task with Daniel]
- Order any enclosures needed?
- Order parts (connectors, cables) required
- Power HV [Daniel is lead, with guidance from Kurtis]
- Make cable
- Study response with oscilloscope
- Mini-PC preparation [Daniel is lead, with guidance from Matt]
- Linux load
- USB, ethernet config status?
- Revised system diagram (to post here)
Summary
slides
(work needed) -- to feed into Poster