Minutes of the BEAST meeting
Wednesday September 9th 11:00 JST
The installation of the BEAST frame at KEK was completed.
The system test of BEAST detectors at Hawaii was finished.
Schedule:
Haba reported on the last KEK-B meeting. The delays in vacuum pipe
delivery have been resolved. Now the item on the critical path
are the septum magnets required for beam transport from the linac
to the main ring. The first one will be ready in late October and
the last one in late November. This delay for delivery of these magnets
could lead to a one month delay in startup of accelerator
commissioning (mid-december). The leaders of
the accelerator division are working hard
to find a way to expedite the delivery of these magnets from
the company and avoid this additional delay.
Commissioning strategy:
There was then a discussion of how to handle the bakeout period
where large radiation doses are expected. A proposal is given below:
1) Install the full BEAST including the SVD quadrant
on the beampipe starting next week.
2) Debug BEAST readout and DAQ as soon as the first
low current turns are accumulated at KEK-B.
3) As the beam current increases, (around 100 mA)
measure radiation dose and background levels.
If the radiation dose is not acceptable remove
BEAST. Wait until high current bakeout is completed.
Then reinstall BEAST. Otherwise, if the dose during
bakeout is tolerable, continue with BEAST in place
(and possibly turn off power to the diodes and SVD quadrant.)
Since the mechanical installation takes 1-2 days,
this plan is very flexible. In addition, it
will get BEAST readout debugged, provide better feedback
to the accelerator.
Structure and Construction:
Rosen, Haba and IHI completed the installation of the beampipe
support and BEAST frame at the interaction point. Extra bracing
was added to make the structure rigid to better than 0.5mm. The
CsI(Tl) shelves are assembled and ready to be installed.
System Test:
Sahu reported on the system test of the BEAST detectors. About half
of the diodes require conditioning with power on. The leakage
currents go down from 30 nA to around 2 nA after conditioning.
Drift tubes tests show that one tube out of 53 cannot hold high voltage.
There was a mistake in mechanical assembly of the quadrants
for the system test at Hawaii. This will be corrected at KEK.
The location of the amplifier boxes
for the drift tubes and power distribution will be simplified when
the detectors are installed at KEK.
Simulation:
Yamamoto reported on work with TURTLE. He has now resolved a long
standing problem, the discrepancy between the beam size in the
TURTLE simulation and the SAD calculation. This problem and other
related problems are due to having neglected dispersion in the
TURTLE calculation. See his e-mail.
CsI(Tl):
Zhilich presented a proposal for CsI(Tl) DAQ which is available
in an earlier e-mail message.
DAQ:
Gordon and Moffit have arrived at KEK and have begun work.