Minutes of the BEAST meeting
Friday September 25th 12:00 JST

The inner and outer BEAST detectors were installed at KEK. Photos are available on the BEAST WEB page.

  • Schedule:

    Haba reported that no changes to the schedule have been reported. KEK-B startup around November 10th is expected. The next KEK-B steering committee meeting is October 1st. At this meeting the final schedule will be announced.

  • Installation:

    Sahu reported that the inner and outer BEAST detectors have been installed. The drift tube HV and signal cables were attached. The preamp PC board boxes were installed on shelves. The MOSFETS and diodes are being cabled.

  • Diode readout:

    Varner reported that 2 more PCB readout boards were completed. 1 spare will be made soon. Next week he will check the calibration of the high gain portion of the diode readout circuit.

  • Spares:

    Rosen is supervising the construction of a spare drift tube quadrant, 10 spare MOSFETs and 4 spare diodes.

  • DAQ:

    Gordon and Moffit reported that they were able to make histograms of drift tube counts. The DAQ components seem to be functioning.

  • Simulation:

    Rodriguez showed results on the GEANT simulation of BEAST. All the detector components except for the EFC are done. The beampipe and water cooling needs minor revisions. He also discussed work on digitization of the BEAST signals. He is able to make histograms of energy deposited and numbers of hits/event in the detector components. For the simulation of SVD occupancy, the default GEANT step size may be too large. He is currently using a 3 microsec integration time for the calculation of detector response.

  • Future work:

    We then discussed what remains to be done for the BEAST experiment: Finish debugging and calibration of BEAST detector components. Establish DAQ communication with KEK-B. Install crystals abd finalize CsI(Tl) DAQ. Finish full TURTLE+GEANT simulation of BEAST.