Minutes of the BEAST meeting
Friday January 22nd 12:00 JST
Schedule :
At the last KEK-B steering committee, the commissioning
run was extended until March 5. Further extensions of the run
are possible but not yet decided. The next meeting on
scheduling is February 15th. Constraints on the schedule include
power consumption and the dedicated photon factory run.
KEK-B General:
Currently, a major problem is the reproducibility
of linac settings when switching from e+ to e-. Stable currents in both the
HER and LER of over 10 mA have been achieved. The maximum
current is limited by radiation safety. After the installation of
Lambertson magnets for the abort system, this is no longer a
constraint. At present, the emphasis is making collisions before
the end of January. We should therefore
prepare the EFC back to back trigger to be ready for collisions.
For BEAST we have had one long coast for LER background
measurement at a current of below 1 mA. A higher current LER fill
is needed for a good first determination of the LER background.
Closer cooperation between BEAST and KEK-B is needed in the future.
Haba-san said that a joint workshop is planned around the week
of February 15th.
Shifts and Data Taking:
We will not record NTUPLEs during KEK-B machine experiments. The
BEAST DAQ will run with run number=0 and the shifter still must be present
to keep the DAQ alive, reset HV trips etc.
Once stable fills are routine, we will record all BEAST data.
We have requested help from the cosmic ray shift crew to man BEAST
shifts in the coming months.
SVD Ladders in BEAST:
The question discussed was whether SVD ladders in BEAST are needed
to determine whether BELLE can be rolled in. Without SVD ladders,
we will depend entirely on simulation to determine the SVD occupancy.
Bozek noted that real beam is needed to fully test
the sparsification algorithm. He noted that the DAQ/readout
for the BEAST ladders can be considerably simpler than
the DAQ used in the cosmic ray setup. Yamamoto discussed CLEO 2.5
problems that did not become apparent until after the SVX was installed
with beam. This problems were related to timing in high occupancy
events. Olsen noted that Peter Weilhammer had recommended that we
get experience with real SVD ladders in beam as soon as possible.
However, to install and readout ladders will require resources from
the SVD group, a plan and a schedule. The BEAST group requests that
this question be discussed and decided at the next executive board meeting.
BEAST Hardware Status:
Diodes:
Sahu reported on current hardware problems. During high background
commissioning, 3 of the 24 PIN diodes were killed. One was lost due
during HER commissioning when the tungsten collimator was in place.
Two others were lost during the start of LER commissioning. During
these high background tuning periods, a conductive path is
established across the diode which makes it impossible to deplete
the diode. To avoid this problem in the future, the 60 V depletion
voltage has been reduced to 3 V until stable fills are achieved.
The signals from the diodes will still be useful for accelerator tuning.
(Recall the depletion depth is proportional to sqrt(V), so 1/4
of the wafer is depleted). In addition,
Marc Rosen will prepare spare diode assemblies which can be
installed during a future down time.
MOSFETs:
The integrated doses is now 20 krad from commissioning. The more
sensitive R-type MOSFETs will soon run out of dynamic range.
Two MOSFETs have been installed on the EFC. MOSFETs should also
be installed on the CsI(Tl) crystals.
Drift Tubes:
The HV calibration has been done. The radiation dose calculated
from the drift tube leakage current agrees with the diode dose
to within a factor of two. To preserve the drift tubes, the high
voltage has been reduced from the optimal 1.8-1.9 kV range to 1.6
kV. The trip current is currently been set to 10 microA. This can
probably be increased to 100 microA.
X-ray detector:
A 32 channel pulse inverter was constructed. Amplifier and ADC were
found. Now trying to get spectra.
EFC:
The scalers for the EFC are now understood. 2/8 scalers appear to be
dead. This is under investigation.
DAQ Status:
Moffit reported that no DAQ crashes have been reported during recent
shifts. Bugs in NTUPLE filling have been corrected. Problems with
out of range IOTECH channels are fixed. The BEAST display has been
updated to take the lower diode voltage into account.
Simulation:
Bozek reported on simulation work to understand the December 25th
HER BEAST run. Taking into the account the vacuum pressure which was
x 2 greater than previously assumed, and the 5 mm offset of the beam
in the vertical direction, the simulation is within a factor of 2 of
the observed Background/current/nTorr.
However, he is unable to
reproduce the angular distributions and front/back diode ratio with
the GEANT simulation. Sahu's EGS simulation with lower energy cutoffs
however reproduces the observed front/back ratio well.
The effect of the vertical emittance (x 5 greater than nominal)
on the background appears to be small. The effect of showering
upstream of the nominal GEANT volume should be checked.