Minutes of BEAST meeting
Thursday April 16th (8:00 a.m. JST)
Background simulation:
Sahu has nearly completed the high energy ring
(HER) DECAY TURTLE calculation with the new lattice.
He is checking alphas, betas, beam sizes for the 150 lattice elements
through which he tracks off energy particles. The background appears
to be much lower than for the last lattice but this needs
to be checked in detail.
When the DECAY TURTLE part is finished, Bozek will take it
and incorporate it into the GEANT simulation of BELLE.
Sahu and graduate student Sanjay Swain will optimize the positions
of the moveable masks. The approximate locations
of the moveable masks are now known from communications with Toge
and Haba.
Sources:
Haba-san has been looking into calibration sources. Cd^109,
t_1/2=462 days, which decays via e- capture to Ag^109 with the
emission of 25 KeV x-ray is the best candidate. The X-ray should be
transmitted through the Al in the proportional tubes.
Haba and Sahu will calculate the necessary strength to achieve
a few Hz counting rate in the tubes. The proportional tubes are
0.5" diam (1.27 cm) and 20 mil (0.0508cm) thick. Location and the
number of sources is still to be determined.
Structure:
Marc Rosen (UH engineer) is working on the mechanical drawing
and design. Haba is worried about checking the consistency with the drift
chamber endplates and other mechanical constraints. A trip to KEK
by Rosen to check out the mechanical constraints for installation
and his presence at the time of BEAST installation was strongly requested.
Information from KEK-B
The issue of pressure bumps was discussed again. The pumps are
connected in series in 15-17m sections. Some discussion is required
with the accelerator group so that individual pumps can be turned
off to make local pressure bumps in order to diagnose sources of beam background.
Schedule on subcomponents:
Diodes:
100 Hamamatsu diodes have been ordered. Graduate student Yong Li
will begin the radiation and temperature calibration of the diode/thermistor packages
at the UH Papaya Irradiation Facility when the diodes arrive at the end of April.
Proportional Tubes:
Tubes have been ordered
MOSFETs, CsI(Tl), EFC:
No news
SVD:
On schedule. Ladders in May. Electronics will be ready by August.
Installation:
Current plan is to install BEAST around August 10, 1998.
Next commissioning meeting: Thursday April 23 (8:00 a.m. JST)